Rental guide · Updated 2026-11-20
How to Plan a Temporary Job Site Basecamp Rental, Step by Step
For project managers and superintendents: how to turn a crew size and a schedule into a basecamp order, from bunk bed trailers and shower-restroom combos to laundry, an office combo, and utilities, on one quote.

Key points
- Start with the headcount, shifts, and rotation length.
- Size showers by OSHA's 1-per-10 ratio where showers are required, and toilets by OSHA's construction table.
- A complete camp gets a project schedule; a single unit sets up in about an hour.
A basecamp is a small town built for a project. Getting it right starts with three numbers: how many people sleep on site, how many work each shift, and how long the rotation lasts.
1. Beds
Sleeper and accommodation units come in contractor, VIP, and shared layouts. Supervisors often take the 20ft Accommodation (VIP); crews take the 20ft Accommodation (Contractor) or the 20ft Accommodation (Labor Shared).
2. Showers and restrooms
Where an OSHA standard requires showers, OSHA 1910.141 sets one shower for each 10 employees of each sex. For toilets, OSHA 1926.51 Table D-1 calls for one where there are 20 or fewer workers, then one toilet seat and one urinal per 40. A 30ft Luxury Shower-Restroom Combination Trailer (10 Individual Stalls) covers a large crew at shift change.
3. Laundry and food
Rotations longer than a week need a 30ft Laundry Trailer (10 Washer/Dryer). A camp that feeds itself adds a kitchen and refrigeration.
4. The site office
The Office, Sleeper and Shower & Restroom Trailer combines a site office, a sleeping room, and a shower-restroom for a superintendent or a small crew.
5. Utilities and schedule
Every unit needs power, water, and a wastewater plan. A single trailer sets up in about an hour once on site with utilities ready; a whole camp is scheduled around site preparation, access, utilities, inspections, and review. See our turnkey workforce housing page for the complete-camp option.
Sources
- OSHA 1910.141: Sanitation (general industry): Where a standard requires showers: one shower for each 10 employees of each sex, hot and cold water, soap, and individual towels.
- OSHA 1926.51: Sanitation (construction): Table D-1: one toilet for 20 or fewer workers; one toilet seat and one urinal per 40 workers above that.
Links checked 2026-11-20. Figures quoted above appear on the linked pages.